Building Department
Building Inspections
Once you have obtained a building permit, you may begin work. Several inspections are required on most construction. A sample rule is to call for an inspection before you cover anything up. On a typical residence, you will need the following inspections.
| Footing and Steel Inspection | To be made after trenches are excavated. Forms are erected and steel is in place and tied. |
| Foundation Inspection | To be made after forms are erected and steel is in place and tied. |
| Drain and Water | To be made after all plumbing is installed and prior to the covering of any drainage or water pipes and pressure test is on before basement floor is poured. |
| Rough Plumbing | To be made after all plumbing is installed and prior to the covering of any drainage or water pipes and pressure test is on. |
| Rough Electrical | To be made after all wiring is in place and before any of it is covered up. |
| Rough Framing | To be made after the roof, all framing members, fire block, etc. are in place, and all pipes, vents and electrical wiring are installed |
| Rough Mechanical | To be made after flue and ducts are run; furnace is installed and gas lines sized and in place. |
| Gas Pressure Check | We must verify - pump to 20 psi pressure test |
| Lath and/or Wallboard Inspection | To be made after all lathing and/or wallboard, interior and exterior, is in place (but before any plastering is applied), and before wallboard joints and fasteners are taped and finished. |
| Chimney Inspection | To be made while the chimney is being constructed - between the time it passes through the ceiling, but prior to the time it passes through the roof. |
| Stucco Certification | Must be signed by installer and general contractor; then filed with building office. |
| Final Inspection | To be made after building is completed and prior to occupancy. |
To schedule an inspection, call 435-755-1650, and give the following information:
1) The name that is listed on the permit as the owner.
2) The address as listed on the building permit.
3) The type of inspection needed.
4) What time if day that the inspection is desired. If you
have scheduled concrete, state the projected time.
Please note that all times are approximate times. The uniform building code requires 24 hours notice.